Energy audit at Gas
Company (UP) |
|
|
| |
| Executive Summary |
| |
| In UP there is a Gas company with India’s largest
gas based Petrochemical Complex with an installed capacity
of 2,60,000 TPA of Polyethylene ( HDPE, LDPE and LLDPE). The
major by products are LPG, C2/C3 and Propane.
Natural Gas and electricity are the main sources of energy
used in the plant. PCRA carried out a comprehensive energy
conservation study for operations /performance of both electrical
and thermal energy intensive equipments of the plant . The
study was to identify potential areas of energy conservation
and recommend energy savings measures along with cost benefit
analysis.
PCRA’s audit finding highlights potential electrical
and thermal savings as given below - |
- Electrical savings of Rs. 58.16 lacs at an investment
of Rs.55.46 lacs with a simple pay back period of 0.95
years from our 6 proposals (i.e 1163.6 MWH or 107.4 KLOE)
- Thermal savings of Rs. 1261.37 lacs at an investment
of Rs.359 lacs with a simple pay back period of 0.28 years
from our 9 proposals (i.e 12154.6 KLOE), covering the
following areas.
|
- Electrical system network
- Motive load
- Air compressor
- Boiler operations
- Steam distribution network
- Furnace operation
- GTs, HRSG and steam turbine operations
- Lighting system
- Cooling water and allied systems.
- Illumination
|
Content (79 pp) |
| |
- Executive summary
- Introduction
- Study of transformers
- Study of motive load
- Study of compressor
- Study of lighting system
- Study of boilers
- Study of steam trap
- Study of furnace
- Study of GTs & HRSGs
- Study of steam turbine
- Steam distribution and utilities
|
Annexure
|
| |
| For further information, please write to:
Director (I/C),
PCRA, Sanrakshan Bhawan,
10, Bhikaji Cama Place,
New Delhi-110066
Tel : +91-11-26198856
Fax: +91-11-26109668
Web site: www.pcra.org |
|
|
| Powered by: Webdunia |
© Petroleum Conservation Research
Association, India |
|