 |
| |
|
|
|
| |
| |
Energy Audit at Dairy
plant at Mehsana,Gujarat. |
|
|
| |
| |
A comprehensive
energy conservation study of the Dairy plant at Mehsana,Gujarat
was carried out by PCRA.This Dairy is engaged in the manufacture
of various qualities of milk & also other milk products
like butter, ghee, as well as milk powder in their plant.
The milk processing capacity of the plant is 18
lakh litres per day. There are 6 nos. boilers of various capacities
using natural gas as fuel for generating steam for use in
the plant. The boilers use both furnace oil & natural
gas as fuel. Natural gas is also used as fuel in powder plant
air heater .There are 4 powder plants with air heaters of
various capacities Natural gas is generally used as fuel in
the air heaters. Annual natural gas consumption is 123.25
Lakh NM3. Annual furnace oil consumption is 3329 MT.The unit
takes its electricity supply from the GEB .The contract demand
is 2400KVA.The unit has also installed 8 nos. GG sets of capacities
125, 380 & 750 KVA operating on natural gas which generates
electricity in the plant. Electricity is consumed in a variety
of equipment in the refrigeration plant compressors &
auxiliary equipment like cooling & chilled water pumps,
powder plant blowers, air compressors, water & milk pumps
& lighting.
A comprehensive energy conservation study
of the plant was carried out by PCRA, The identified total
annual energy saving potential is around Rs. 148.76 Lakhs
on a recurring basis. The energy audit has identified several
areas for energy conservation in thermal & electrical
energy. The steps identified for energy conservation are given
below:
- The excess air percentage on all the boilers on natural
gas firing is quite high. This is due to the fact that
the natural gas pressure varies. Due to this the air –
gas ratio also varies resulting in high excess air levels
& low combustion efficiencies. By installing an online
oxygen monitoring & control system, the efficiency
of the boiler will improve on both natural gas & furnace
oil firing. The savings on furnace oil are to the tune
of 3% at least.
- Furnace in the main storage tank is heated by steam
coils. This results in churning of the
furnace oil & does not allow the moisture present
in the furnace oil to settle down. It is recommended that
steam heating in the main storage tank be stopped. It
is also recommended that the furnace oil storage &
service tanks should be drained at least once a week.
This will ensure that all the water is removed from furnace
oil & prevent sludge formation.
- Furnace oil main storage tanks should be cleaned at
least once a year to remove the sludge
accumulated at the bottom of the tanks.
- Steam line insulation is not in good shape in the plant.
All the valves & flanges are not insulated in the
plant. Also some bare steam lines were observed. By insulating
with 2" thick mineral wool with aluminium cladding,
90% of the heat loss can be minimised.
- A steam trap survey was conducted in the plant. Steam
traps identified as leaking /blocked should be rectified
immediately.
- It is recommended that the steam pressure powered pumps
be installed from the two sections
identified. This will enable the condensate to be pumped
to the boiler house as soon as it is formed. This will
raise the boiler feed water temperature by at least 20
deg c.
- It is recommended that the air heater be tuned to reduce
the excess air levels. Also the flue gas
temperature observed in both the air heaters is on the
higher side. It is recommended that the air heaters be
checked for leakages & cleaned. This will reduce the
flue gas temperature to at least 230 deg c.
- Even after cleaning/servicing of air heaters, the flue
gas temperature will be in the range of 230 deg c. It
is recommended that airpreheaters be installed on the
hot air generators to preheat combustion air. The flue
gas temperature after the air preheater can be brought
down to 110 deg c. The savings due to this will be 5%.
The air preheaters have to be installed on all the hot
air generators.
- It is observed that the hot air flow to both the dryers
seems to be on the higher side.It is recommended that
the hot air flow be reduced on a trial basis for both
the plants & the hot air generation temperature be
increased to 185 deg c. This will result in appreciable
natural gas savings & power savings.
- It is recommended that for N2 plant Supply air fan
& milk pump, soft starters should be installed
before reducing the size of the motor. This is due to
the fact that the starting torque is quite high &
soft starter is essential to take up the initial high
torque. SAF fan motor size is presently 125 HP. It can
be reduced to 75 HP after installation of a soft starter.
- Chilled water is sent to the plant at 1- 2 deg c &
comes back to the refrigeration section at 7 -8 deg c.
It is sent to the ice bank tank directly in the main plant.
In the glycol plant , the chilled glycol is sent to the
instant chiller . The chilled glycol evaporator temperature
is – 10 deg c. The main refrigeration plant has
a single - 10 deg c ammonia refrigeration system. It is
recommended that the load be handled by a 2 stage system.
Ammonia from the -2 deg c accumulator be used in the instant
chillers & ammonia from the -5 deg c accumulator be
used in the IBT & for other loads. The glycol plant
should be operated at 0 deg c suction saturation temperature.
- It is observed that the in cream pasteurizers , cream
chilling is done from 57 deg c to 7 deg c by chilled water.
It is recommended that an intermediate cooling water section
be included in the cream pasteurizers. This will bring
down the milk temperature to 35 deg c. The milk can then
be chilled to 7 deg c from 35 deg c. This will drastically
reduce the chilling load on the chilled water system.
- It is recommended that the 100 TR PHE condenser pump
impeller be trimmed by 10%. This will
reduce the power consumption in the pump.
- It is to be noted that the 200 TR condenser pumps have
a rated head of 22 metres as against that of 10 metres
for the 100 TR condenser pump. It is recommended that
this pump be replaced by a pump with similar capacity
but lower head around 10 metres. This will reduce the
power consumption in the pumps by 30-40%.
- It is observed that milk is underchilled in the plant.
During the audit study, we observed pasteurized milk temperatures
ranging from as low as 1 deg c to 12 deg c. This is a
direct loss in terms of steam as well as of refrigeration
capacity. It is recommended that the plant personnel be
more vigilant & throttle the chilled water valves
incase the milk flow in the pasteurizers is not as per
the rated capacity of the unit.
- It is observed that the milk temperature rises quite
appreciably in the pasteurized milk silos in the plant.There
is a rise in the milk temperature of at least 5 -6 deg
c in an 8 hour period as per the plant personnel. This
was also confirmed by the moisture condensation observed
on the surface of the milk silos. This increases the refrigeration
load unnecessarily.
- It is observed that the insulation of chilled water
supply & return lines to N3/N4 is quite poor as seen
from the moisture condensation on the surface of the lines.
It is recommended that the insulation be upgraded at the
earliest.
- It is recommended that the compressed air requirement
for N1/N2 plant should be met by the central plant screw
compressors. The central compressor room is very close
to the N1/N2 plant & hence minimum length of new line
will need to be put up. Savings due to utilization of
screw compressors over reciprocating compressors will
be at least 10% due to the fact that the reciprocating
m/cs are belt driven & the screw m/cs are direct driven.
- Present lighting single phase voltage is 250 to 260
volts. Nowadays lighting transformers are available, which
reduce the voltage to around 220 volts. The reduction
in voltage also reduces power consumption with little
reduction in lumens emitted by the light source. The savings
due to installation of lighting transformer is 30% of
the power consumption.
- It is recommended to replace the existing 4 feet fluorescent
tubes with Asian “E+” energy efficient tubelights.
Power consumption of these tubelights is 28 Watts.
|
|
|
| |
| For further information, please write to:
Director (I/C),
PCRA,
Sanrakshan Bhawan, 10,
Bhikaji Cama Place,|
New Delhi-110066
Telephone: +91-11-26198856
Fax. +91-11-26109668
Web site: www.pcra.org |
|
|
| Powered by: Webdunia |
© Petroleum Conservation Research
Association, India |
|