 |
| |
|
|
|
| |
| |
Energy Audit at Dairy
plant at Bharuch,Gujarat. |
|
|
| |
| |
A comprehensive
energy conservation study of the Dairy plant at Bharuch,Gujarat.
was carried out by PCRA.This Dairy is engaged engaged in the
manufacture of various qualities of milk & also other
milk products like butter, ghee, in their plant. The total
Annual production of the plant Milk – 14892.8 MT,Ghee
– 78.3 MT,Butter - 74.8 MT There are 2 nos. boilers
of capacity 2 TPH each for generating steam for use in the
plant. The boilers use natural gas as fuel for generating
steam .One boiler is in operation & the other is kept
as standby. Annual natural gas consumption is 172301 NM3.
The unit takes its electricity supply from the GEB .The contract
demand is 250KVA. Electricity is consumed in a variety of
equipment in the refrigeration plant compressors & auxiliary
equipment like cooling & chilled water pumps, air compressors,
water & milk pumps & lighting.
A comprehensive energy conservation study
of the plant was carried out by PCRA, The identified total
annual energy saving potential is around Rs. 7.84 on a recurring
basis. The energy audit has identified several areas for energy
conservation in thermal & electrical energy. The steps
identified for energy conservation are given below:
- The excess air level in all the boilers is satisfactory.
However, some fine tuning can be done such
that the oxygen % in the flue gases is 3.0%. This will
result in improvement in boiler efficiency.
- Boiler blowdown is manual for the boiler. The raw water
quality has been tested & the TDS level in
raw water is around 1200 ppm. Boiler water TDS is observed
to be around 10000 ppm as against the permissible level
of 3500 ppm. This will lead to wet steam to the process
& increase in steam
leakages from PRVs/flanges as well as malfunctioning of
PRV valves.
- The high TDS level in the boiler will also lead to increase
in flue gas temperature due to scale deposition on the
water side of the boiler. It is recommended that the r.o
plant be rectified as soon as possible to preserve the
life of the boiler.
- Steam line insulation was in good shape in the plant
in. However, some the valves & flanges on the PRV
stations are not insulated in the plant. Also some bare
steam lines were observed. It is
recommended that the bare valves/flanges/steam lines be
insulated in the plant.
- Presently, no condensate recovery is conducted in the
plant. Ammonia discharge gases from the
refrigeration compressors are at a temperature of over
120 -130 deg c. It is recommended that this waste heat
be used to generate hot water at 70 deg c for boiler feed
water as well as for CIP purpose.
- The power factor of the plant is not satisfactory.
The average power factor for the plant is 0.984.It is
recommended that the power factor be improved to 0.999.
This will result in savings in electrical bills due to
increase in rebate amount.
- The contract demand for the plant is 250 KVA. The minimum
billable maximum demand is 213
KVA. It is observed that the actual maximum demand for
the plant has never crossed 203 KVA. It is recommended
that the contract demand be reduced to 180 KVA. The actual
maximum demand can be kept below 180 KVA even in peak
season by proper scheduling of process machinery.
- It is observed that both the condenser pumps &
all the air compressors are overloaded. It is
recommended that the pumps/motors be inspected & serviced.
The condenser pumps are overloaded largely due to scale
formation on the impeller profile. This is due to the
raw water quality which has TDS of upto 1200 ppm. It is
recommended that the impeller be serviced/replaced.
- It is recommended that new KC-2 compressors be procured
& operated & the leased refrigeration
compressors be phased out to save on lease rentals.
- Presently, there are no liquid level controllers in
the IBT accumulators. Thus there is liquid
carryover into the compressor suction. It is recommended
that liquid level controllers be fitted on the IBT accumulators.
- It is recommended that compressor should be operated
such that the suction pressure is between 30 – 40
psig. Thus, when the suction pressure reaches 30 psig,
one cylinder should be cut-off. The
cylinder should once again be loaded when the suction
pressure reaches 40 psig.
- It is observed that there is thick scale formation
on the ammonia condenser tubes . Moreover one
condenser coil is leaking & is hence not operational.
Hence the discharge pressure of the compressor is on the
higher side. The unit is replacing the leaking coil shortly.
It is further recommended that the condenser coils be
descaled completely. The unit is also advised to restart
the r.o plant.
- It is observed that a section of the ammonia suction
lines from cold store & deep freeze are
uninsulated. This results in the ammonia vapor picking
up unnecessary superheat from the
atmosphere & waste of energy. It is recommended that
the ammonia suction lines be insulated.
It is observed that the insulation of the chilled water
supply & return lines to & the from the process
is damaged. It is recommended that the lines be insulated
properly to reduce refrigeration load on the system.
- It is recommended that the Ahu blowers in milk cold
store & butter deep freeze be shut off along
with the ammonia supply to the AHu coils ,when the desired
room temperature is attained.
- Compressed air is generated at a pressure of 6 to 8.5
kg/cm2g. It is recommended that the
compressed air generation pressure range should be 6 –
6.5 kgc/cm2g. This will result in power
savings in compressed air generation. The unit is already
thinking in this direction & has a proposal for increasing
the compressed air line size to 2” . This will be
sufficient to take care of the pressure drop in the line
& will enable the unit to reduce the generation pressure
to 6.5 kg/cm2g.
- The volumetric efficiency of the air compressor no.1
is not satisfactory. It is recommended that the compressor
be overhauled/serviced to increase its volumetric efficiency.
It is recommended that pump up tests be conducted for
all the compressors as it is a good indicator of the wear
& tear that occurs in the compressor.
- Present lighting single phase voltage is 250 to 260
volts. Nowadays lighting transformers are
available, which reduce the voltage to around 220 volts.
The reduction in voltage also reduces power consumption
with little reduction in lumens emitted by the light source.
The savings due to
installation of lighting transformer is 30% of the power
consumption.
|
|
|
| |
| For further information, please write to:
Director (I/C),
PCRA,
Sanrakshan Bhawan, 10,
Bhikaji Cama Place,|
New Delhi-110066
Telephone: +91-11-26198856
Fax. +91-11-26109668
Web site: www.pcra.org |
|
|
| Powered by: Webdunia |
© Petroleum Conservation Research
Association, India |
|