 |
| |
|
|
|
| |
| |
Energy Audit at Dairy
plant at Anand, Gujarat |
|
|
| |
| |
A comprehensive
energy conservation study of the Dairy plant at Anand, Gujarat
was carried out by PCRA.This Dairy is engaged in the manufacture
of various qualities of milk viz. standard, gold &
pasteurised milk & also other milk products like butter,
ghee, as well as milk powder in their plant. The
milk processing capacity of the plant is 10 lakh litres per
day.There are 4 nos. boilers of various capacities using natural
gas as fuel for generating steam for use in the plant. The
annual consumption of natural gas is 50 Lakh NM3 . Natural
gas is also used as fuel in powder plant air heater .There
are 3 powder plants with air heaters of various capacities
The natural gas consumption of the air heater is also around
51.48 lakh Nm3.
The unit takes its electricity supply from
the GEB .The contract demand is 3000KVA.The unit has also
installed 2 nos. GG sets of 380 KVA operating on natural gas
which generates electricity in the plant.
Electricity is consumed in a variety of equipment in the refrigeration
plant compressors & auxiliary
equipment like cooling & chilled water pumps, powder plant
blowers, air compressors, water & milk
pumps & lighting.
A comprehensive energy conservation study
of the plant was carried out by PCRA, The identified total
annual energy saving potential is around 139.55 lacs on a
recurring basis. The energy audit has identified several areas
for energy conservation in thermal & electrical energy.
The steps identified for energy conservation are given below:
- The excess air levels in the boiler was very high. It
is recommended that the unit procure a combustion gas analyzer
as this will help in maintaining & optimising the boiler
efficiency.
- It is recommended that an autoblowdown controller be
installed on the boiler. This will optimise the boiler water
TDS to 3500 ppm & thus reduce chances of water carryover
along with the steam.
- It is observed that the flue gas temperature for the
10 TPh boiler is quite high at 225 deg C on natural gas
firing. It is recommended that an economiser or a preheater
should be installed to preheat boiler feed water /combustion
air. This will result in savings of natural gas.
- Steam line insulation is not in good shape . All the
valves & flanges are not insulated in the plant. Also
some bare steam lines were observed. By insulating with
2" thick mineral wool with aluminium cladding, 90%
of the heat loss can be minimised.
- A steam trap survey was conducted in the plant. Steam
traps identified as leaking /blocked should be rectified
immediately.
- It is recommended that the condensate should be pumped
automatically from the F-60 & F-35 powder plants &
also Amul 3 process. Online conductivity meters should be
installed for F-60 & F-35 to check for condensate contamination.
This will increase the boiler feed water temperature by
at least 20 deg C.
- Excess air levels were found to be high in F - 60 air
heaters. It is recommended that the air heaters be tuned
to minimise excess air.
- There is tremendous air infiltration into the F - 35
air heaters thus increasing the excess air levels. However,
as the air heaters are of single pass model, even if the
air infiltration is brought down, the flue gas temperature
will increase & their efficiency will remain constant
at around 60%. The F - 35 plant is not in operation most
of the time & thus the replacement of these air heaters
is not warranted. In case, the cheese whey production starts
in full swing in the F -35 plant, then it is recommended
that the air heaters be replaced by new modern air heater,
thereby increasing its efficiency by at least 33% resulting
in savings in natural gas.
- Presently milk is preheated from 8 - 10 deg c to 70 deg
c progressively in tube bundles fitted in each calendria
or a separate heat exchanger in the calendria. The milk
passes from the last calendria to the first calendria picking
up heat. It is proposed that the milk be preheated externally
thus reducing/eliminating steam load for milk preheating.
- A few motors in the plant were found to be under loaded.
If the load on these motors is constant, the motors can
be replaced by lower HP motors from the store/inventory.
Alternatively, the motors should be connected permanently
in star connection. This is because the efficiency of the
motors when operating on low loads is better in star mode
than in delta mode.
- Chilled water is sent to the plant at 1- 2 deg c &
comes back to the refrigeration section at 7 -8 deg c. It
is chilled to 2-4 deg c in the PHE instant chillers- PHE+shell
& then sent to the Ice building tank. Both these refrigeration
loads are handled by a single - 10 deg c ammonia refrigeration
system. It is recommended that the load be handled by a
2 stage system. Ammonia from the -2 deg c accumulator be
used in the instant chillers & ammonia from the -5 deg
c accumulator be used in the IBT & for other loads.
- It is recommended that the air conditioning cooling loads
in the plant be catered to by installing a
double effect vapor absorption system based on high pressure
steam.
- It is recommended that evaporative condensers be fitted
for the refrigeration systems. This will
drastically reduce the power consumption in the pumping.
- A low cost option is to replace the cooling tower pumps
& the condenser pumps with lower head
pumps. Presently the rated head of the pumps is 20 meters.
They can be replaced with pumps of 8 meters rated head.
The savings will be reduced to 40 KW. However, the investment
levels will be highly reduced.
- It is observed that the temperature in cold store /deep
freezes is controlled manually. It is
recommended that auto temperature control switches be installed
for shutting of ammonia solenoid valves incase the cold
store/deep freeze temperature has been achieved.
- Present lighting single phase voltage is 250 to 260 volts.
Nowadays lighting transformers are available, which reduce
the voltage to around 220 volts. The reduction in voltage
also reduces power consumption with little reduction in
lumens emitted by the light source. The savings due to
installation of lighting transformer is 30% of the power
consumption.
- It is recommended to replace the existing 4 feet fluorescent
tubes with Asian “E+” energy efficient tubelights.
Power consumption of these tubelights is 28 Watts.
|
|
|
| |
| For further information, please write to:
Director (I/C),
PCRA,
Sanrakshan Bhawan, 10,
Bhikaji Cama Place,|
New Delhi-110066
Telephone: +91-11-26198856
Fax. +91-11-26109668
Web site: www.pcra.org |
|
|
| Powered by: Webdunia |
© Petroleum Conservation Research
Association, India |
|